Echuca Holiday Park

  • Project typeBuildings
  • Project value$1,600,000
  • Project scheduleConstruction and installation
  • Completion Date30 June 2023
holiday park

Council adopted the Echuca Holiday Park Master Plan in April 2019. 

The master plan identified multiple projects over several years for long term growth.

Landscaping, electrical, cabin, shower and toilet facility upgrades have been completed.

In 2023 further works will be completed at the Holiday Park as part of the ongoing masterplan including new accessible cabins, play areas, solar panels and an upgrade to the amenities block.

As of 30 June 2023:

  • Solar panels have been installed.
  • Play area construction is currently underway.
  • Water park and accessible cabins have been ordered.

This is an ongoing program until 2028.