Council accelerates urgent works for flood-damaged roads

Published on 08 March 2023

Road closures

Campaspe Shire Council has established a panel of contractors to accelerate the urgent repair of flood-damaged roads across the shire.

Campaspe Shire Mayor Cr Rob Amos said fixing flood-damaged roads, bridges, drainage and other road infrastructure is a high priority of the Council so residents, farmers and businesses can return to their normal travel routines and transport arrangements as soon as possible.

“We started urgent remedial road works last year as soon as the water receded and in February, Council appointed a panel of contractors to fast-track the government-funded emergency works which need to be completed by the end of April,” Cr Amos said.

“Our contractors have a big job ahead of them but we are well advanced with the scoping of works and bundling of works packages ready for roll out.

“Of the 1,300-plus Council-owned damaged road segments, we’ve assessed and scoped 850 for repair.

“More than 470 segments require emergency or immediate works, more than 170 segments have been awarded to contractors and additional packages of works are currently being reviewed by panel contractors as part of the award process.”

Road works scheduled over the next few weeks include:

  • removal of the temporary levee constructed on Headworks Road, Torrumbarry
  • roll out of a bridge debris removal package at multiple sites
  • repair / replacement of damaged stormwater pit lids in Rochester and Echuca
  • continued works to earthen, gravel and sealed roads, and drainage structures in Rochester, Bamawm, Colbinabbin, Echuca Village, Koyuga, Fairy Dell, Rushworth and Torrumbarry.

While these state and federally funded emergency works are underway, Council’s ongoing road construction and maintenance activities, as part of the Capital Works Program, will continue.

The second stage of remedial flood-related road works is expected to take up to two years to complete.

Tagged as: