Rushworth Streetscape Stage 2

  • Project typeCapital renewal
  • Project value$2 million
  • Project schedule30 March 2024
  • Contractor nameEarthworks Civil & Construction
  • Completion Date30 March 2024
Rushworth-20180328-1247.jpg

This project will see footpath, kerb and road pavement updates along High Street, Rushworth. The works will be split into six stages to minimise the impact on residents and community members. The stages are:

  • Stage 1 – Footpath and kerb works on the western side of High Street from Wigg Street to Bendigo Bank COMPLETED
  • Stage 2 – Footpath and kerb works on the western side of High Street from Bendigo Bank to the north side of the Railway Line COMPLETED
  • Stage 3 – Footpath and kerb works on the western side of High Street from the north side of the Railway Line to Moora Road COMPLETED
  • Stage 4 – Road pavement works on the western side of High Street
  • Stage 5 – Footpath and kerb works on the eastern side of High Street adjacent to the Post Office
  • Stage 6 – Road pavement works on the eastern side of High Street

The works have been scheduled to finish in time for the Easter Heritage Festival 2024.

 

 

Location

High Street, Rushworth 3612  View Map